Question ID 10856

You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to
create a project plan for an upcoming project for a new customer.
The project is similar to one recently completed for an existing customer. You have the project files
from the completed project.How would you copy the tasks from the completed project without copying the dates and times?

Option A

By opening the existing project and selecting Save As.

Option B

By opening the existing project and modifying the Global Template.

Option C

By opening the existing project, saving the task list in Excel and running the Import Wizard for
the new project.

Option D

By opening the existing project and adding the new project as a subproject.

Option E

By opening the new project and adding the existing project as a subproject.

Correct Answer C
Explanation