Question ID 10856 | You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to |
Option A | By opening the existing project and selecting Save As. |
Option B | By opening the existing project and modifying the Global Template. |
Option C | By opening the existing project, saving the task list in Excel and running the Import Wizard for |
Option D | By opening the existing project and adding the new project as a subproject. |
Option E | By opening the new project and adding the existing project as a subproject. |
Correct Answer | C |