Question ID 10848 | You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to |
Option A | The duration of the Software Coding task has taken 8 days more than forecast. |
Option B | The duration of the Software Coding task has taken 8 days less than forecast. |
Option C | The Software Coding task was completed 8 days later than forecast. |
Option D | The Software Coding task was completed 8 days earlier than forecast. |
Correct Answer | B |
Question ID 10849 | You work as a Project Manager at ABC.com. You are using Microsoft Office Project Professional |
Option A | The duration of the Software Coding task has taken 2 days more than forecast. |
Option B | The duration of the Software Coding task has taken 2 days less than forecast. |
Option C | The Software Coding task is 2 days late. |
Option D | The Software Coding task is 2 days early. |
Correct Answer | C |