Question ID 10854

You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to
create a project plan.
The project plan must be suitable for project resources who work different hours and different
days. Some resources work Monday to Friday 8 hours a day. Some resources work 4 hours in the evenings from Monday to Friday. Some resources work 12 hour shifts at the weekends.
What should you include in your project plan?

Option A

You should include a summary task for each shift.

Option B

You should include a timeline for each shift.

Option C

You should include a base calendar for each shift.

Option D

You should create a resource pool for each shift.

Correct Answer C
Explanation


Question ID 10855

Your work at ABC.com includes management of projects using Microsoft Project Professional
2010.
A resource named Mia Hamm is assigned to multiple tasks in the project. Mia needs to book some
time off during the project. She has booked 7 days off and emails you her vacation dates.
How should you modify the project schedule to show the impediments that result from Mia’s time
off?

Option A

You should select all the tasks that Mia is a assigned to and use the Move function to move the
tasks forward by one week.

Option B

You should select all the tasks that Mia is a assigned to and use the Move function to move the
tasks back by one week.

Option C

You should modify the resource calendar for Mia by changing the working time.

Option D

You should select all the tasks that Mia is a assigned to and move and add 7 days to the finish
date.

Correct Answer C
Explanation