Question ID 10854 | You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to |
Option A | You should include a summary task for each shift. |
Option B | You should include a timeline for each shift. |
Option C | You should include a base calendar for each shift. |
Option D | You should create a resource pool for each shift. |
Correct Answer | C |
Question ID 10855 | Your work at ABC.com includes management of projects using Microsoft Project Professional |
Option A | You should select all the tasks that Mia is a assigned to and use the Move function to move the |
Option B | You should select all the tasks that Mia is a assigned to and use the Move function to move the |
Option C | You should modify the resource calendar for Mia by changing the working time. |
Option D | You should select all the tasks that Mia is a assigned to and move and add 7 days to the finish |
Correct Answer | C |