Question ID 10850

You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to
manage a project to development a new software system for a customer.
You enter a manually scheduled task named System Requirements Definition and enter a finish
date for the task of 20th July.You assign a resource named Clive Allen to the System Requirements Definition task. You discover that the properties of the task have changed. The finish date has now changed to 27th
July and the task mode has changed to automatically scheduled.
What should you do to identify the cause of the changes?

Option A

You should view the resource calendar in the Task Inspector utility.

Option B

You should view the project calendar in the Task Inspector utility.

Option C

You should run the Level Resource utility.

Option D

You should click Update Project.

Correct Answer A
Explanation


Question ID 10851

You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to
manage a project.
The project consists of two major phases. You have used all 10 baselines in phase1 of the project.
Phase1 is nearly complete. You now need to create another baseline for phase2. You plan to clear
the existing baselines used in phase1. However, you would like to save baseline10 as baseline1
before clearing the remaining baselines.
Which of the following actions should you take?

Option A

You should run the Set Baseline utility and select Set Interim Plan. Select Baseline10 in the
Copy field and select Start1/Finish1 in the Into field.

Option B

You should run the Set Baseline utility and select Set Interim Plan. Select Start10/Finish10 in
the Copy field and select Start1/Finish1 in the Into field.

Option C

You should run the Set Baseline utility and select Set Interim Plan. Select Baseline10 in the
Copy field and select Baseline1 in the Into field.

Option D

You should run the Set Baseline utility and select Set Interim Plan. Select Start10/Finish10 in
the Copy field and select Baseline1 in the Into field.

Correct Answer C