READ Free Dumps For Microsoft- 70-236
Question ID 10850 | You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to |
Option A | You should view the resource calendar in the Task Inspector utility. |
Option B | You should view the project calendar in the Task Inspector utility. |
Option C | You should run the Level Resource utility. |
Option D | You should click Update Project. |
Correct Answer | A |
Question ID 10851 | You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to |
Option A | You should run the Set Baseline utility and select Set Interim Plan. Select Baseline10 in the |
Option B | You should run the Set Baseline utility and select Set Interim Plan. Select Start10/Finish10 in |
Option C | You should run the Set Baseline utility and select Set Interim Plan. Select Baseline10 in the |
Option D | You should run the Set Baseline utility and select Set Interim Plan. Select Start10/Finish10 in |
Correct Answer | C |