READ Free Dumps For Microsoft- 70-236





Question ID 10852

You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to
manage a project.The project has been in progress for 5 months. The current phase is taking longer than projected
in the original baseline schedule.
How can you display the current project schedule and the baseline schedule side-by-side for
comparison?

Option A

By displaying the Gantt with Timeline chart.

Option B

By displaying the Tracking Gantt chart.

Option C

By displaying the project calendar.

Option D

By displaying the default Gantt chart.

Option E

By displaying the Task Usage chart.

Correct Answer B
Explanation


Question ID 10853

You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to
manage a project.
The project schedule includes multiple independent networks of tasks with dependencies. You are
viewing the default Gantt chart.
How can you configure the view to display the critical tasks of all the networks of tasks with the
project?

Option A

By selecting the Show Warnings option in the Inspect task utility.

Option B

By selecting the Calculate multiple critical paths check box in the Project 2010 options.

Option C

By selecting Critical from the Filter drop-down box on the View tab.

Option D

By selecting Critical from the Group drop-down box on the View tab. q

Correct Answer C
Explanation