Question ID 10846

You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to
manage a project.You are in the process of viewing the Gantt chart for the project. You would, however, like to only
view the tasks on the critical path of the project.
Which of the following actions should you take?

Option A

You should consider choosing Critical from the Highlight Filter drop-down box on the View tab.

Option B

You should consider choosing Critical from the Filter drop-down box on the View tab

Option C

You should consider choosing Critical from the Group drop-down box on the View tab.

Option D

You should consider choosing the Critical Tasks checkbox on the Format tab.

Correct Answer B
Explanation


Question ID 10847

You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to
manage a project.
While monitoring the project schedule, you notice that a red man icon has appeared next to one of
the tasks in the project schedule. You would like to discover the icon’s purpose.
Which of the following actions should you take?

Option A

You should consider applying a Late Tasks filter to the Gantt chart view.

Option B

You should consider double clicking the task to view the task information.

Option C

You should consider selecting View > More Views > Task Details Form to view the task details.

Option D

You should consider selecting Inspect Task on the Tasks tab.

Correct Answer C