Question ID 10844

Your work at ABC.com includes management of projects using Microsoft Project Professional
2010.How can you display a task that lists the project name, total project duration and start and finish
dates by default in the project schedule?

Option A

By navigating to the Format tab and selecting the Critical Tasks checkbox.

Option B

By navigating to the Format tab and selecting the Summary Tasks checkbox.

Option C

By navigating to the Format tab and selecting the Project Summary Task checkbox.

Option D

By navigating to the Format tab and selecting the Outline Number checkbox.

Correct Answer C
Explanation


Question ID 10845

You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to
manage a project.
You have added three subtasks named Drawings, Prototype and Review to a summary task
named Design. You want the ability to monitor and compare the actual progress of the tasks to the
original projected schedules. To this end, you have created a number of baselines for the tasks.
Which three of the following steps should you take to update Baseline1 for the three subtasks
only?

Option A

Highlight the Drawings, Prototype and Review subtasks.

Option B

Highlight the Design summary task.

Option C

Click Set Baseline and select Baseline1.

Option D

Select the Selected Tasks radio button.

Option E

Select the Entire Project radio button.

Option F

Select the To all summary tasks checkbox.

Correct Answer A,C,D
Explanation