Question ID 10840

You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to
manage a new project.
The resources in the project work from 6pm to 10pm four days a week from Monday through
Thursday.
You have been instructed to create a new default calendar for the project so that the working
hours of the part-time resources are reflected.Which of the following actions should you take?

Option A

You should modify the Standard calendar then select the Update Project option.

Option B

You should navigate to the Change Working Time window and click Create New Calendar.
Then change the calendar type in the Project Options dialog box.

Option C

You should change the calendar type to part-time in the Project Options dialog box.

Option D

You should navigate to the Change Working Time window and change the calendar type to
part-time.

Correct Answer B
Explanation


Question ID 10841

Your work at ABC.com includes management of projects using Microsoft Project Professional
2010.
You are configuring the tasks for a new project. You notice that the default constraint type for
tasks that you create is set to As Soon As Possible. You are required to make sure that the default
constraint type for new tasks is changed to As Late As Possible
Which of the following actions should you take?

Option A

You should configure the Schedule From option in the Project Information window to Project
Finish Date.

Option B

You should configure the Schedule From option in the Project Information window to Project
Finish Date.

Option C

You should check the New Tasks are effort driven check box in the Project Options.

Option D

You should select all tasks then click the Update Project option.

Correct Answer A
Explanation