Question ID 10838 | Your work at ABC.com includes management of projects using Microsoft Project Professional completed by 15th July. You want the default Gantt chart to show 20th July as the completion date |
Option A | Open the task information window and enter 20th July in the Constraint date field. |
Option B | Open the task information window and enter 20th July in the Deadline date field. |
Option C | Open the task information window and select the Fixed Units option in the Task Type field. |
Option D | Open the task information window and enter 20th July in the Finish date field. |
Correct Answer | B |
Question ID 10839 | You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to |
Option A | You should configure five summary tasks each with a duration of 36 days. |
Option B | You should set the Status Date to 180 days into the future. |
Option C | You should enter the project timescale in the project calendar. |
Option D | You should create a single summary task with the manually scheduled option. |
Correct Answer | C |