Question ID 10842

You work as a Project Manager at ABC.com. You are using Microsoft Office Project Professional
2010 to manage a project.
Task1 is represented by the following icon in the default Gantt Chart view:

Task2 is represented by the following icon in the default Gantt Chart view:
What would you need to change to configure Task2 to be the same type as Task1?

Option A

You would need to configure Task2 to be automatically scheduled.

Option B

You would need to configure Task2 to be manually scheduled.

Option C

You would need to configure Task2 as critical.

Option D

You would need to configure Task2 as a milestone.

Correct Answer B
Explanation


Question ID 10843

Your work at ABC.com includes management of projects using Microsoft Project Professional
2010.
You are calculating the timescales for a new project using the bottom-up scheduling method. You
have created three tasks named Drawings, Prototype and Review.
You want to group the Drawings, Prototype and Review tasks into a project phase named Design.
How would you group the three tasks?

Option A

By selecting the three tasks and clicking the Outdent Task option.

Option B

By selecting the row above the three tasks and entering a new Summary Task.

Option C

By selecting the three tasks and clicking the Indent Task option.

Option D

By selecting the three tasks and selecting the Insert Summary Task option.

Correct Answer D
Explanation