Question ID 20936 | How many roles make up the Project Board? |
Option A | One |
Option B | Two |
Option C | Three |
Option D | Four |
Correct Answer | C |
Question ID 20937 | Which of the following statements about stakeholders are true? |
Option A | Only 1 is true |
Option B | Only 2 is true |
Option C | Both 1 and 2 are true |
Option D | Neither 1 or 2 are true |
Correct Answer | C |