Question ID 20888

Which product records any project outcomes perceived as negative by stakeholders?

Option A

Business Case

Option B

Project Plan

Option C

Communication Management Strategy

Option D

Project Product Description

Correct Answer A
Explanation


Question ID 20889

What is an off-specification?

Option A

A new requirement

Option B

A quality tolerance

Option C

A type of issue

Option D

A major risk

Correct Answer C
Explanation