READ Free Dumps For PRINCE2- PRINCE2





Question ID 20894

What takes place during the Closing a Project process?

Option A

The post-project benefits reviews are performed

Option B

Ownership of the project's products is transferred to the customer

Option C

An End Stage Report is prepared for the final stage

Option D

The project closure notification is reviewed and approved

Correct Answer B
Explanation


Question ID 20895

Which is an objective of the Closing a Project process?

Option A

Prepare the plan for the next stage

Option B

Assess any benefits that have already been realized

Option C

Produce a Benefits Review Plan to identify what benefits are expected

Option D

Check that all benefits are realized before closing a project

Correct Answer B
Explanation