Question ID 20894 | What takes place during the Closing a Project process? |
Option A | The post-project benefits reviews are performed |
Option B | Ownership of the project's products is transferred to the customer |
Option C | An End Stage Report is prepared for the final stage |
Option D | The project closure notification is reviewed and approved |
Correct Answer | B |
Question ID 20895 | Which is an objective of the Closing a Project process? |
Option A | Prepare the plan for the next stage |
Option B | Assess any benefits that have already been realized |
Option C | Produce a Benefits Review Plan to identify what benefits are expected |
Option D | Check that all benefits are realized before closing a project |
Correct Answer | B |