Question ID 20904

What process is used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances?

Option A

Directing a Project

Option B

Controlling a Stage

Option C

Managing a Stage Boundary

Option D

Managing Product Delivery

Correct Answer B
Explanation


Question ID 20905

In which product does a Project Manager define the time and cost tolerances for the work to be done by a Team Manager?

Option A

Product Description

Option B

Team Plan

Option C

Work Package

Option D

Stage Plan

Correct Answer C
Explanation