Question ID 20904 | What process is used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances? |
Option A | Directing a Project |
Option B | Controlling a Stage |
Option C | Managing a Stage Boundary |
Option D | Managing Product Delivery |
Correct Answer | B |
Question ID 20905 | In which product does a Project Manager define the time and cost tolerances for the work to be done by a Team Manager? |
Option A | Product Description |
Option B | Team Plan |
Option C | Work Package |
Option D | Stage Plan |