Question ID 20890 | Which is a type of issue? |
Option A | A lesson |
Option B | A request for change |
Option C | An Exception Report |
Option D | A risk with an estimated high impact |
Correct Answer | B |
Question ID 20891 | Which is a typical core activity within configuration management? |
Option A | Quality assurance |
Option B | Risk management |
Option C | Verification and audit |
Option D | Progress reporting |
Correct Answer | C |