Question ID 20902

Which is a purpose of the Controlling a Stage process?

Option A

Assign work to be done and take corrective action to ensure that the stage remains within tolerance

Option B

Provide a fixed reference point at which acceptance for the project product is confirmed

Option C

Enable the Project Board to be provided with sufficient information to authorize the next stage

Option D

Enable the organization to understand the work that needs to be done to deliver the project's products

Correct Answer A
Explanation


Question ID 20903

What process is used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances?

Option A

Directing a Project

Option B

Controlling a Stage

Option C

Managing a Stage Boundary

Option D

Managing Product Delivery

Correct Answer B
Explanation