Question ID 20902 | Which is a purpose of the Controlling a Stage process? |
Option A | Assign work to be done and take corrective action to ensure that the stage remains within tolerance |
Option B | Provide a fixed reference point at which acceptance for the project product is confirmed |
Option C | Enable the Project Board to be provided with sufficient information to authorize the next stage |
Option D | Enable the organization to understand the work that needs to be done to deliver the project's products |
Correct Answer | A |
Question ID 20903 | What process is used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances? |
Option A | Directing a Project |
Option B | Controlling a Stage |
Option C | Managing a Stage Boundary |
Option D | Managing Product Delivery |
Correct Answer | B |