Question ID 20900

What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?

Option A

Directing a Project

Option B

Managing a Stage Boundary

Option C

Controlling a Stage

Option D

Starting up a Project

Correct Answer C
Explanation


Question ID 20901

Which process is triggered towards the end of the final stage when all the assigned work has been completed?

Option A

Managing a Stage Boundary

Option B

Managing Product Delivery

Option C

Closing a Project

Option D

Controlling a Stage

Correct Answer C
Explanation