Question ID 20900 | What process ensures focus on the delivery of a stage's products and avoids uncontrolled change? |
Option A | Directing a Project |
Option B | Managing a Stage Boundary |
Option C | Controlling a Stage |
Option D | Starting up a Project |
Correct Answer | C |
Question ID 20901 | Which process is triggered towards the end of the final stage when all the assigned work has been completed? |
Option A | Managing a Stage Boundary |
Option B | Managing Product Delivery |
Option C | Closing a Project |
Option D | Controlling a Stage |
Correct Answer | C |