Question ID 20932 | Which does the Executive need to ensure is in place before the project is initiated? |
Option A | All Work Packages are authorized |
Option B | An understanding of how the project will contribute to corporate objectives |
Option C | The Project Plan has been approved |
Option D | The Project Initiation Documentation is complete |
Correct Answer | B |
Question ID 20933 | Which project management team member represents the interest of those who will operate the project's products to realize the benefits after the project is complete? |
Option A | Executive |
Option B | Senior User |
Option C | Senior Supplier |
Option D | Project Manager |
Correct Answer | B |