READ Free Dumps For PRINCE2- PRINCE2





Question ID 20934

What product is used to maintain a record of those who have an interest in the project and their information requirements?

Option A

Project Plan

Option B

Communication Management Strategy

Option C

Project Brief

Option D

Project Product Description

Correct Answer B
Explanation


Question ID 20935

Identify the missing word in the following sentence. A member of the Project Board is responsible for [ ? ] assurance.

Option A

quality

Option B

supplier

Option C

risk

Option D

product

Correct Answer D
Explanation