Question ID 20928 | When should the Project Board refer to corporate or programme management for a decision? |
Option A | The stage requires resources |
Option B | It is forecast that project level tolerance will be exceeded |
Option C | The Senior Supplier or Senior User needs to be changed |
Option D | Any request for change needs to be approved |
Correct Answer | B |
Question ID 20929 | Identify the missing words in the following sentence. At the end of a stage, the [ ? ] should be used to check whether there is a requirement to send copies of the End Stage Report to external interested parties. |
Option A | Stage Plan |
Option B | Communication Management Strategy |
Option C | Follow-on action recommendations |
Option D | Quality Management Strategy |
Correct Answer | B |