Question ID 20928

When should the Project Board refer to corporate or programme management for a decision?

Option A

The stage requires resources

Option B

It is forecast that project level tolerance will be exceeded

Option C

The Senior Supplier or Senior User needs to be changed

Option D

Any request for change needs to be approved

Correct Answer B
Explanation


Question ID 20929

Identify the missing words in the following sentence. At the end of a stage, the [ ? ] should be used to check whether there is a requirement to send copies of the End Stage Report to external interested parties.

Option A

Stage Plan

Option B

Communication Management Strategy

Option C

Follow-on action recommendations

Option D

Quality Management Strategy

Correct Answer B
Explanation