READ Free Dumps For PRINCE2- PRINCE2
Question ID 20930 | Which is NOT a purpose of the Organization theme? |
Option A | Define a project management team structure |
Option B | Define the level of tolerance for each level of the project management team |
Option C | Define the Project Board's responsibility for directing the project |
Option D | Define which role is accountable for the project's success |
Correct Answer | B |
Question ID 20931 | Which is NOT represented by one of the three primary categories of stakeholder identified in PRINCE2? |
Option A | Those with a financial interest in the project |
Option B | Those who will manage the project on a day-to-day basis |
Option C | Those who will specify the desired outputs of the project |
Option D | Those who will create the project's outputs |