Question ID 20924 | Which process covers the work done by external suppliers who may NOT be using PRINCE2? |
Option A | Closing a Project |
Option B | Managing a Stage Boundary |
Option C | Managing Product Delivery |
Option D | Directing a Project |
Correct Answer | C |
Question ID 20925 | Which two roles are linked by the Managing Product Delivery process? |
Option A | Corporate or programme management and Project Board |
Option B | Project Board and Project Manager |
Option C | Project Manager and Team Manager |
Option D | Team Manager and external supplier |
Correct Answer | C |