READ Free Dumps For PRINCE2- PRINCE2
Question ID 20920 | Which is a purpose of the Managing Product Delivery process? |
Option A | Enable the Senior Supplier to be provided with sufficient information by the Project Manager so that they can review the success of the current Work Package |
Option B | Provide a controlled link between the Project Manager and the Team Manager(s) |
Option C | Enable the Project Board to request updates to the current Team Plan |
Option D | Establish solid foundations for the project |
Correct Answer | B |
Question ID 20921 | From whom does a Team Manager obtain approval for a completed product? |
Option A | Project Manager |
Option B | Project Support |
Option C | The authority defined in the Product Description |
Option D | Senior Supplier |
Correct Answer | C |