Question ID 20914 | Which is NOT a purpose of the Initiating a Project process? |
Option A | Enable a Project Board decision about the commitment of resources to a project |
Option B | Enable an organization to understand the work that needs to be done to deliver a project's products before a project is approved |
Option C | Establish solid foundations for a project |
Option D | Enable the Project Board to decide whether it is worthwhile to initiate a project |
Correct Answer | D |
Question ID 20915 | Which of the following statements about the Project Initiation Documentation are true? |
Option A | Only 1 is true |
Option B | Only 2 is true |
Option C | Both 1 and 2 are true |
Option D | Neither 1 or 2 are true |
Correct Answer | C |