Question ID 20914

Which is NOT a purpose of the Initiating a Project process?

Option A

Enable a Project Board decision about the commitment of resources to a project

Option B

Enable an organization to understand the work that needs to be done to deliver a project's products before a project is approved

Option C

Establish solid foundations for a project

Option D

Enable the Project Board to decide whether it is worthwhile to initiate a project

Correct Answer D
Explanation


Question ID 20915

Which of the following statements about the Project Initiation Documentation are true?
1. The Project Initiation Documentation is used to ensure that a sound basis exists before the Project Board authorizes a project.
2. The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project.

Option A

Only 1 is true

Option B

Only 2 is true

Option C

Both 1 and 2 are true

Option D

Neither 1 or 2 are true

Correct Answer C
Explanation