READ Free Dumps For PRINCE2- PRINCE2





Question ID 20916

Which plan provides the Business Case with costs during the Initiating a Project process?

Option A

Initiation Stage Plan

Option B

Project Plan

Option C

Stage Plan

Option D

Team Plan

Correct Answer B
Explanation


Question ID 20917

Which is the base product against which the Project Board can assess progress, issues and ongoing viability questions?

Option A

Project Brief

Option B

Project Initiation Documentation

Option C

Project mandate

Option D

Benefits Review Plan

Correct Answer B
Explanation