Question ID 20910

Who should act as the communication channel between a project and corporate or programme management?

Option A

Project Board

Option B

Project Assurance

Option C

Project Manager

Option D

Project Support

Correct Answer A
Explanation


Question ID 20911

Which statement about the Directing a Project process is true?

Option A

Provides a mechanism for the Project Board to assure that there is continued business justification

Option B

Covers the day-to-day activities of the Project Manager

Option C

Ensures there are regular progress meetings

Option D

Begins on completion of the Initiating a Project process

Correct Answer A
Explanation