Question ID 20912 | Which of the following statements about the Project Initiation Documentation are true? |
Option A | Only 1 is true |
Option B | Only 2 is true |
Option C | Both 1 and 2 are true |
Option D | Neither 1 or 2 are true |
Correct Answer | C |
Question ID 20913 | Which is an objective of the Initiating a Project process? |
Option A | Develop the corporate quality management system as part of the Project Initiation Documentation |
Option B | Prepare the plans for the subsequent stages |
Option C | Summarize how the organization's project management method will be tailored for the project |
Option D | Request authority from corporate management to deliver the project |
Correct Answer | C |