Question ID 21677

Marty is the project manager of the recently completed NHK Project. The project was deemed successful
by the project customer and they have signed the formal acceptance documentation. Marty has written the
final project report, released the project team, and completed the lessons learned documentation. What
else should Marty do in the closure of the NHK Project?

Option A

Summarize the project variance.

Option B

Archive the project records.

Option C

Summarize the project risks costs.

Option D

Close the project office.

Correct Answer B
Explanation Section: Volume A


Question ID 21678

Which of the following statements is most accurate about the critical path?

Option A

The critical path is always one path that shows the project duration.

Option B

The critical path has no float.

Option C

The critical path is the longest path because it has the most activities.

Option D

The critical path reveals which path has the most risk of failure.

Correct Answer B
Explanation Section: Volume A