Question ID 21683 | You are the program manager of the HNG Program. This program has a budget at completion of
$2,345,900 and is expected to last two years. The program is currently 30 percent complete and you have
spent $789,000. The program is supposed to be 35 percent complete but do to some delays you're slightly
behind schedule. Based on this information, how many pennies is the program losing per dollar invested in
the program work?
|
Option A | 17
|
Option B | 11
|
Option C | 15
|
Option D | 14
|
Correct Answer | B |
Explanation Section: Volume A
Question ID 21684 | You are the program manager for your organization. You have created a program that will create things for
the organization throughout the program not only at program closure. All of the following are elements that
you may transfer to the organization throughout the program's life cycle except for which one?
|
Option A | Benefits
|
Option B | Risk management outcomes
|
Option C | Program personnel
|
Option D | Outputs from team development
|
Correct Answer | C |
Explanation Section: Volume A