Question ID 21679 | You are the program manager for the BHN Program. Your program has 122 stakeholders that you'll need
to plan to communicate with. Considering the size of the program how many communication channels do
you have in this program?
|
Option A | 244
|
Option B | 122
|
Option C | 14,884
|
Option D | 7,381
|
Correct Answer | D |
Explanation Section: Volume A
Question ID 21680 | You are the program manager of the HNG Program. This program has a budget at completion of
$2,345,900 and is expected to last two years. The program is currently 30 percent complete and you have
spent $789,000. The program is supposed to be 35 percent complete but do to some delays you're slightly
behind schedule. Based on this information, what is the schedule variance (SV) of this program?
|
Option A | -$85,230
|
Option B | $821,065
|
Option C | -$284,100
|
Option D | -$117,295
|
Correct Answer | D |