Question ID 21685

You are the program manager for your organization and are planning the program. One of the plans you
need to create will define how you'll transfer the benefits of the program to the operations of your
organization. Which program management plan defines this process?

Option A

Operational transfer plan

Option B

Program transition plan

Option C

Benefits transfer plan

Option D

Program closure plan

Correct Answer B
Explanation Section: Volume A


Question ID 21686

A program has a BAC of $1,750,000 and is expected to last two years. The program is currently at the third
milestone which represents 35 percent of the program work. As it happens, this program has already spent
$620,000 of the budget. Management is concerned that the program may also be slipping on schedule
because the program should be forty percent complete by this time. Based on this information which type
of performing is present in this scenario?

Option A

Schedule, because the program's planned value is only $700,000.

Option B

Cost, because the program has a cost variance of -7,500

Option C

Schedule, because the program has a schedule performance index of .88.

Option D

Cost, because the program has an estimate to complete of $1,151,429.

Correct Answer C
Explanation Section: Volume A