Question ID 21709

Who prepares the statement of work (SOW) for external projects?

Option A

Customer

Option B

Project management team

Option C

Project Manager

Option D

Chief Financial Officer (CFO)

Correct Answer A
Explanation Section: Volume A


Question ID 21710

You are the program manager for your organization. Your current program, which has just been initiated,
needs to launch several projects in order to create all of the benefits of the program. What document do
you need to create in order to initiate the projects within your program?

Option A

Project charter

Option B

Program charter

Option C

Program scope statement

Option D

Project preliminary scope statement

Correct Answer A
Explanation Section: Volume A