Question ID 21705 | Two project managers in your program, Marcy and Mary, are not agreeing with the scheduling of project |
Option A | Conflict |
Option B | Noise |
Option C | Barrier |
Option D | Ad hoc |
Correct Answer | C |
Question ID 21706 | Which of the following is responsible to sign off on the closure documents of a project? |
Option A | Project team members |
Option B | Project Manager |
Option C | End user |
Option D | Sponsor |
Correct Answer | D |