Question ID 21695 | Joan is the program manager for her organization. Management has asked her to create a centralized |
Option A | Program management information system |
Option B | Program management integrated change control |
Option C | Change control systems |
Option D | Program management plan execution |
Correct Answer | A |
Question ID 21696 | You are the program manager for your organization. Your current program, which has just started, has |
Option A | The project managers will use the critical path method for scheduling activities. |
Option B | The project managers will use PERT to schedule all activities. |
Option C | The project managers will use the critical chain method for scheduling activities. |
Option D | The project managers will create Gantt charts to schedule all activities. |