Question ID 21691 | You are the program manager for your organization that utilizes vendors from several different |
Option A | Approve the payment request |
Option B | Finalize the performance report |
Option C | Examine the contract |
Option D | Complete a financial audit of the work |
Correct Answer | A |
Question ID 21692 | You are the program manager for your organization. Your program has a budget of $750,000 and is |
Option A | Negative ten percent |
Option B | .75 |
Option C | $300,000 |
Option D | $225,000 |
Correct Answer | B |