Question ID 21689 | Part of your job as the program manager is to coach the project managers on their duties and goals. One |
Option A | Quality assurance is an inspection-driven process to keep mistakes out of the project. |
Option B | Quality assurance is a prevention-driven process to keep mistakes out of the project. |
Option C | Quality assurance defines quality and sets goals for the project team. |
Option D | Quality assurance is an organization-wide process to do the work according the organizational goals |
Correct Answer | B |
Question ID 21690 | When a change enters your program requirements you must update all of the following documents except |
Option A | Program work breakdown structure |
Option B | Program activity list |
Option C | Program charter |
Option D | Program scope |
Correct Answer | C |