Question ID 21701

You are the program manager for your organization and are working on gathering the requirements for a
new solution and mission statement. There are several instances in the stakeholder pool where the
stakeholders and their manager are being queried on possible requirements. You worry that the
subordinates may have requirements, ideas, and suggestions to offer but they may be not submitting their
thoughts because they do not want to contradict their managers. You believe you need a method to gather
all requirements without the stakeholders having any fear of retribution. Which one of the following allows
you to anonymously gather iterations requirements and still allow for all stakeholders to review what has
been submitted in an attempt to find consensus?

Option A

Delphi Technique

Option B

Focus groups

Option C

Web surveys

Option D

Workshops

Correct Answer A
Explanation Section: Volume A


Question ID 21702

An organization is considering a new program. The program has a cost of $1,950,000 and will last for three
years. What is the minimum future value this organization should expect to receive from this program if it is
initiated and the rate of return is six percent?

Option A

$2,322,481

Option B

$1,950,000

Option C

$2,067,000

Option D

$1,950,001

Correct Answer A
Explanation Section: Volume A