Question ID 21681 | Which of the following documents provides the mandate to execute the program within a certain timeline |
Option A | Program architecture baseline |
Option B | Program risk register |
Option C | Program WBS |
Option D | Program charter |
Correct Answer | D |
Question ID 21682 | In which of the following processes is the program charter created? |
Option A | Establish Program Financial Framework |
Option B | Plan Program Scope |
Option C | Initiate Program |
Option D | Develop Program Management Plan |
Correct Answer | C |