Question ID 21681

Which of the following documents provides the mandate to execute the program within a certain timeline
and also presents milestones for the delivery of products or incremental benefits?

Option A

Program architecture baseline

Option B

Program risk register

Option C

Program WBS

Option D

Program charter

Correct Answer D
Explanation Section: Volume A


Question ID 21682

In which of the following processes is the program charter created?

Option A

Establish Program Financial Framework

Option B

Plan Program Scope

Option C

Initiate Program

Option D

Develop Program Management Plan

Correct Answer C
Explanation Section: Volume A