Question ID 21673 | Your program has a budget at completion of $1,550,000 and is expected to last one year. Currently your |
Option A | The schedule is performing worse because the SPI is .90 |
Option B | The cost is performing worse because the EAC is $1,611,111. |
Option C | The schedule is performing worse because the SV is -$27,500. |
Option D | The cost is performing worse because the CPI is .96. |
Correct Answer | A |
Question ID 21674 | Robert's program is slipping on its schedule and management has asked that Robert find a method to |
Option A | Lead time |
Option B | Crashing |
Option C | Lag time |
Option D | Fast tracking |
Correct Answer | B |