Question ID 21671

You are the program manager for your company and are monitoring and controlling several aspects of your
program. You want to make certain that you're including all areas that need to be monitored and controlled.
Which one of the following is not something you'll have to monitor and control as a program manager?

Option A

Materials required by the program

Option B

Equipment your program uses

Option C

Susan the application developer in your program

Option D

Stakeholder identification

Correct Answer D
Explanation Section: Volume A


Question ID 21672

A program has a budget at completion of $1,250,000 and has already spent $425,000. The program is
running late due to some vendor delays; the program is only 30 percent complete though it was scheduled
to be 45 percent at this time. Based on this information how much more money will this program need to
finish?

Option A

$978,445

Option B

$919,325

Option C

$991,667

Option D

$987,544

Correct Answer C
Explanation Section: Volume A