Question ID 21665

You are the project manager for your organization and are working with the project stakeholders and the
business analyst to define all of the deliverables the project is to create. The stakeholders would like the
option of adding more deliverables later in the project and keeping the requirements somewhat open for
changes. You explain to the business analyst that you need a set of requirements that define exactly what
needs to be delivered for the project. What document are you trying to create in this early stage of the
project?

Option A

Requirements technical documentation

Option B

Project scope statement

Option C

Project charter

Option D

Detail design document

Correct Answer B
Explanation


Question ID 21666

A new program is being initiated for the HNQ Organization. The program manager is working with the
business analyst and management to define several attributes of the program. All of the following are
identified during program initiation except for which one?

Option A

Program risk

Option B

Program benefits

Option C

Program scope

Option D

Link to organizational strategy

Correct Answer A
Explanation