Question ID 10905

You work as a Project Manager at ABC.com. You are using Microsoft Office Project Professional
2010 to manage a project.
You are managing the tasks in the project schedule. The project team members work eight hours
a day, five days a week. They do not work at weekends.
One of the tasks in the project schedule has a duration of 4 days and is at 50 percent. You assign
the task to a resource named Mia. Mia is currently working on another task so she will divide her
time evenly between the two tasks. You set Mia’s assignment units to 50 percent.
How will changing Mia’s assignment units affect the task?

Option A

The Work will show 48 hours.

Option B

The Work will show 40 hours.

Option C

The Remaining work will show 32 hours.

Option D

The Remaining work will show 24 hours.

Option E

The Duration will show 4 days.

Option F

The Duration will show 6 days.

Correct Answer F
Explanation


Question ID 10906

You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to
manage a project.
A task in the project schedule is in progress. You want to remove the current resource assignment
from the task and assign another resource.
How can you replace the existing resource without affecting the task time data, including Work,
Remaining Work and Actual Work?

Option A

You should select the task and run the Task Inspector function.

Option B

You should use the Level Resource function and select the existing resource.

Option C

You should select the new resource in the Resource Name column drop-down list and deselect
the existing resource.

Option D

You should use the Team Planner feature to drag the task to the new resource.

Correct Answer C
Explanation