Question ID 10895

You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to
manage a project.
You are preparing for a monthly meeting of senior management to discuss the progress of a
project. You plan to take your laptop to the meeting and connect it to a projector so that the senior
management can see the progress of the project.
For the purpose of the meeting, you want to simplify the project view. You want to modify the view
to display just the Gantt chart, the task list with the projected completion dates and the percentage
of work done.
Which two of the following functions should you create to produce the required display? (Choose
two.)

Option A

A custom filter.

Option B

A custom table.

Option C

A custom view.

Option D

A custom group.

Correct Answer B,D
Explanation


Question ID 10896

You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to
manage a project.
You have configured the task list. You now need to assign resources to the tasks.
Which two of the following steps should you perform to enable you to drag and drop resources into
a task? (Choose two.)

Option A

You should display the Team Planner view.

Option B

You should display the Gantt Chart view.

Option C

You should click Resource Pool.

Option D

You should click Assign Resources.

Option E

You should click Add Resources.

Correct Answer B,D
Explanation