Question ID 10899

You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to
manage a project.
The project schedule contains manually scheduled tasks. You are in the process of planning the
schedule and assigning resources. Some tasks are yet to be scheduled. You want to assign the
resources to tasks before you schedule them.
Which of the following actions should you take?

Option A

You should consider assigning resources using the Team Planner view.

Option B

You should consider setting the tasks to be automatically scheduled.

Option C

You should consider assigning resources using the Add Resources function.

Option D

You should consider assigning resources using the Substitute Resources function

Option E

You should consider assigning resources using the Replace option in the Assign resources
dialog box.

Correct Answer A
Explanation


Question ID 10900

You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to
manage a project.
The project schedule contains manually scheduled tasks. Multiple resources are assigned to each
task. One of the tasks has a red man icon next to it. When you hold the curser over the red man,
you receive the following error message: "This task has resources assigned which are overallocated."
How can you view recommendations for possible solutions to the problem?

Option A

Select the task and click Level Resource.

Option B

Right-click on the task and select Reschedule to available date.

Option C

Right-click on the task and select Fix in Task Inspector.

Option D

View the task in the Team Planner view.

Correct Answer C
Explanation