Question ID 10897

You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to
manage a project.
The project schedule contains many manually scheduled tasks. The project is becoming larger
than the initial scope, and as a result, additional resources have been assigned.
You have assigned the additional resources to the tasks in the project schedule. You now need to
automatically determine the effect of the extra resources on the finish dates of the tasks, without
modifying the schedule mode of the tasks.
Which of the following actions should you take?

Option A

You should consider making use of the Calculate Project function.

Option B

You should consider adjusting the Scheduled Finish setting.

Option C

You should consider making use of the Level Resource function.

Option D

You should consider making use of the Update Project function.

Correct Answer A
Explanation


Question ID 10898

You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to
manage a project.
The project schedule contains manually scheduled tasks. Multiple resources are assigned to each
task. You are aware that some resources are over-allocated. Additional resources will be assigned
to the project to alleviate the over-allocation.
Which project view would display the resource over-allocation?

Option A

The default Gantt chart view.

Option B

The default Leveling Gantt view.

Option C

The Team Planner view.

Option D

The Task Usage view.

Correct Answer C
Explanation