Question ID 10903 | You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to |
Option A | You should run the Task Inspector function. |
Option B | You should make use of the Replace option in the Assign Resources dialog box. |
Option C | You should rename the resource for Clive to Mia. |
Option D | You should use the Level Resource function. |
Correct Answer | B |
Question ID 10904 | You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to |
Option A | You should create a new resource with the new cost and assign it to the tasks on 5 April 2010. |
Option B | You should update the standard rate for the existing resource on 5 April 2010in the Resource |
Option C | You should set the standard rate for the resource to increase on 5 April 2010in the Resource |
Option D | You should create an additional Resource Cost table to reflect the increase on 5 April 2010. |
Correct Answer | C |