Question ID 10903

You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to
manage a project.
The project schedule contains manually scheduled tasks and automatically scheduled tasks. The
total time for the project is estimated to be six months. Each task has one or more resources
assigned to it. Two of the resources are named Clive and Mia.
Clive has booked two weeks off for vacation. During those two weeks, Mia will be performing
Clive’s tasks.
How should you update the project schedule to accommodate the changes?

Option A

You should run the Task Inspector function.

Option B

You should make use of the Replace option in the Assign Resources dialog box.

Option C

You should rename the resource for Clive to Mia.

Option D

You should use the Level Resource function.

Correct Answer B
Explanation


Question ID 10904

You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to
manage a project.
The cost of a resource that has been assigned to a task will increase on 5 April 2010.
How should you configure the total project cost to automatically update to reflect the increased
costs?

Option A

You should create a new resource with the new cost and assign it to the tasks on 5 April 2010.

Option B

You should update the standard rate for the existing resource on 5 April 2010in the Resource
Cost table.

Option C

You should set the standard rate for the resource to increase on 5 April 2010in the Resource
Cost table.

Option D

You should create an additional Resource Cost table to reflect the increase on 5 April 2010.

Correct Answer C
Explanation