Question ID 10901

Your work at ABC.com includes management of projects using Microsoft Project Professional
2010.
A number of tasks in the project schedule require a lot of travel from the project team members.
How should you configure the project schedule to record the total cost of travel associated with
each task?

Option A

You should add a new resource, select Cost for the resource type with the Budget and Generic
checkboxes unchecked.

Option B

You should add a new resource, select Cost for the resource type, and then check the Budget
checkbox.

Option C

You should add a new resource, select Cost for the resource type, and then check only the
Generic checkbox.

Option D

You should add a custom field for each task to record the travel costs.

Correct Answer B
Explanation


Question ID 10902

You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to
manage a project.
The project schedule contains many scheduled tasks. Some tasks are automatically scheduled
and some tasks are manually scheduled. Multiple Work and Material resources are assigned to
each task.
How can you make sure that there are no over-allocated resources in the project?

Option A

You should consider making use of the Level All option in the resource leveling section.

Option B

You should consider making use of the Task Inspector function.

Option C

You should consider configuring all tasks to be manually scheduled.

Option D

You should consider sharing the Resource Pool.

Correct Answer A