READ Free Dumps For Microsoft- 70-178
Question ID 10893 | You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to |
Option A | You should select Save View on the View tab to save the view to the Global.mpt file. |
Option B | You should run the Links Between Projects feature on the Project tab to create a link from the |
Option C | You should run the Links Between Projects feature on the Project tab to create a link from the |
Option D | You should insert the other projects as subprojects of the project with the custom view. |
Correct Answer | A |
Question ID 10894 | You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to |
Option A | You should consider making use of the Group by Active v. Inactive option. |
Option B | You should consider making use of the Group by Complete and Incomplete Tasks option. |
Option C | You should consider making use of the Group by Duration option. |
Option D | You should consider making use of the Group by Critical option. |
Correct Answer | D |