READ Free Dumps For Microsoft- 70-178
Question ID 10889 | You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to |
Option A | You should access the Format tab, select Bar Styles, and then select Noncritical tasks. |
Option B | You should access the View tab, select Highlight, and then select Noncritical tasks. |
Option C | You should access the Format tab, select Text Styles, and then select Noncritical tasks. |
Option D | You should access the Format tab, select Task Views, and then select Noncritical tasks. |
Correct Answer | C |
Question ID 10890 | Your work at ABC.com includes management of projects using Microsoft Project Professional2010. |
Option A | You should open a new project in Task Sheet view and paste in the task outline. |
Option B | You should open a new project and run the Import Outlook Tasks function. |
Option C | You should copy the task outline to a text file and save the file with the .mpp file extension. |
Option D | You should copy the task outline to a text file and save the file as a comma separated values |
Correct Answer | C |