Question ID 10883

You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to
create a project plan for a new project for a customer named Weyland Industries.
You have a task list in an email. You want to create the project schedule in Microsoft Project 2010
using the task list in the email.
How should you create the project schedule?

Option A

You should copy the tasks from the email and paste them into a new project schedule.

Option B

You should export the tasks from the email to a Microsoft Excel spreadsheet then import the
tasks into Project 2010.

Option C

You should copy the tasks from the email and paste them into a Microsoft Excel spreadsheet
then import the tasks into Project 2010.

Option D

You should copy the tasks from the email and paste them into a Microsoft Excel spreadsheet
then save the spreadsheet as a Project Template file.

Correct Answer A
Explanation


Question ID 10884

You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to
create a project plan for a new project for a customer named Weyland Industries.You plan to use a task list from a SharePoint 2010 site. The tasks in the list on the SharePoint site
do not have a start date or end date.
How can you ensure that no start date or end date is configured when you create the tasks in the
project schedule?

Option A

By using the New from SharePoint Task List option when creating the new project schedule.

Option B

By selecting the tasks in the project schedule and clicking the Manually Schedule button on the
Task ribbon.

Option C

By selecting Manually Scheduled for the New tasks created option in the Project Options.

Option D

By selecting the tasks in the project schedule and clicking the Auto Schedule button on the
Task ribbon.

Option E

By selecting Automatically Scheduled for the New tasks created option in the Project Options.

Correct Answer C
Explanation